Project Timeline
Early Development & Initial Studies
Early development efforts began, including finalizing the project footprint and conducting initial viability studies from both a land and interconnection perspective.
Project Acquisition by Atlantica
Atlantica Sustainable Infrastructure acquired the Osseo Solar project from its previous developer, taking over all development activities.
Environmental Studies & Permitting Preparation
Atlantica completed Wetland Delineations and began working with Stantec to prepare the Conditional Use Permit. Initial engineering designs commenced in September 2025, and a meeting with Trempealeau County was held in December to discuss the contents of the permit.
Cultural Resources & WDNR Review
Phase 1 Cultural Resource Assessment began in January 2026. In February, the WDNR Environmental Review was completed. Work also began on the Vegetation Management Plan, Landscape Plan, Sound Studies, and Decommissioning Plans.
Community Outreach & Open Houses
On May 6th, 2026, Atlantica hosted an Open House at Grand Occasions from 6–8pm. A second Open House for the community of Sumner Township and Osseo is planned for June 2026.
Conditional Use Permit Submission
Atlantica plans to submit the Conditional Use Permit to Trempealeau County. This is a key regulatory milestone required before construction can begin.
Estimated date subject to change.
Geotechnical Work
Atlantica begins geotechnical investigations across the project area to assess soil conditions and inform final foundation and racking system design.
Estimated date subject to change.
Final Engineering Design
Atlantica begins 305 engineering design work, finalizing all technical specifications required for construction procurement and permitting compliance.
Estimated date subject to change.
Construction
Construction of the Osseo Solar facility begins, including civil works, panel installation, electrical infrastructure, and grid connection activities.
Estimated date subject to change.
Commercial Operation
The Osseo Solar facility achieves Commercial Operation Date (COD), delivering clean renewable energy to the grid and generating long-term economic benefits for Trempealeau County and surrounding communities.
Estimated date subject to change.